Civil Construction Review Schedule

  • All construction drawings shall be submitted by Friday at Noon to be considered for the following week review cycle. 
  • First and Second review comments will be due 12 business days after submittal. 
  • Third (and subsequent) review comments will be due 7 business days after submittal. 