NC 55 Turn Lane (Avent Ferry to Main Street)

NC55 Turn LaneTransportation Bond Project

This project involves adding a new right turn lane southbound on N.C. 55 to improve traffic flow onto South Main Street. The Town has secured more than $500,000 in federal funds for the project.

Location:

N.C. 55 southbound from Avent Ferry Road to Main Street

Status:

  • Under construction
  • Completion is expected in 2026

Completed:

  • Construction plans & specifications
  • Construction authorization from NCDOT
  • Duke Energy removed streetlights along southbound N.C. 55 between Avent Ferry Road and Main Street in preparation for turn lane construction. Streetlights will be relocated following construction.    

Public engagement:

Public engagement meetings held in July and December 2019.

Key partners:

Holly Springs staff has engaged with key partners for this project, including:

  • North Carolina Department of Transportation
  • Capital Area Metropolitan Planning Organization
  • Duke Energy
  • United States Army Corps of Engineers/North Carolina Division of Environmental Quality